Just three weeks to go until the new National League North season kicks off and we are more than a little excited here at Mill Farm!
Our dedicated team have been working tirelessly behind the scenes, seven days a week, to get the stadium ready for the start of the new campaign.
In Churchill’s Function Suite the feature ceiling is finished, complete with decoration and lighting, whilst the room is ready for its penultimate coat of paint. The granite bar top is also in production and is soon to be fitted.
The feature ceilings in the toilets for the suite have been completed whilst tiling has also started.
The kitchens for Churchill’s and Milano’s restaurant have been cladded, the huge extractor hoods are in place and the resin flooring will be laid over the weekend.
The tiling of the first floor foyer has begun and the impressive marble tiling of the main entrance has been completed this week.
Back of house all home and away showers are in and the changing room lockers in the home area are all but finished, complete with spotlights over each player! No pressure then lads!