Momentum is building as we approach the opening of the Bradley’s Sports Bar and Aroma Café early next month.

Internal work is progressing well and the finishing items are starting to be installed.

The tiled apron around the base of the café bar has been completed, whilst the distressed oak herringbone feature wooden floor is 75 per cent down.

Over the weekend the decorators are in to give the café the first coat of paint of the final colours.

The first fix plumbing for the toilets on the ground floor of the West Stand is done and the sound system and lighting tracks have been installed this week.

Some of the high quality walnut doorframes have been fitted and the mosaic tiling to the back of the bar will start on Monday.

The central area of Bradley’s bar has been laid with slate flooring and that is 90 per cent complete.

Glazing to the pitch side of the West Stand is almost complete and next week should see the AFC Fylde signage and the clock go up.

Preparation work for the block paviours at the main entrance has started and work on the impressive spiral staircase in the lobby starts early next week.

On the pitch, drainage and irrigation is complete whilst half of the playing surface has been covers with a soil and nutrient rootzone carpet.