Work on the playing surface at Mill Farm has been on going over the past couple of weeks and now that the area has been levelled, soil is beginning to be laid.

The soil started to be transferred from the bottom of the site on to the pitch yesterday and will be levelled out over the next few weeks before drainage work can begin.

West Stand
More glass has been fitted on the road side elevations and screening to the road side is set to start soon.

Plastering is well underway on the ground floor whilst plaster boarding is on going on the second floor where Milano restaurant and Churchill’s conferencing suite are situated.

Tiling has begun in the toilet and shower rooms in the home changing area to the right of the player’s tunnel.

Fire separation is underway between the floor levels. 

South Stand
Terracing and steelwork is complete and blockwork has started.

East Stand
Brickwork started this week and the black cladding to the rear of the stand, facing the road, is over half complete and is expected to be finished in around a week.

Click on the images below to enlarge