As we head into the festive period, construction at Mill Farm continues to power on through the difficult weather conditions.

One of the big differences you will notice this week has been the erection of the floodlight masts towering over the East Stand. The curved masts are state-of-the-art and look very impressive as you can see.

The steelwork for the East Stand is expected to be finished before Christmas.

In the West Stand, the concrete flooring on the roof, second floor and first floor is complete and the ground floor is expected to be finished by early next week. The walls also have started to go up on the first floor.

The terracing at the front of the stand is well on the way to completion and we are hopefully that too will be finished by the time Santa comes down the chimney!

See our gallery below – click image to enlarge.